" ... allow ... commercial developers to use land at Fort Irwin to construct a solar power plant there between 2013 and 2022. ... will provide power to both the civilian power grid in California, and to Fort Irwin, home of the Army's National Training Center."
" ... the Army will provide to the developers, for as many as 50 years, up to 14,000 acres of land. .. Army receives rent for the land through cash or in-kind services."
" ... facility with both concentrated solar thermal and photovoltaic technology. ... will be built in phases, with a project end date expected around 2022. But Phase 1A of the project, with a completion of around 2014, is expected to provide enough power to sustain Fort Irwin."
Via: US Army LINK